Form GSA 184B, Construction Progress Report (Change Order Breakdown)

FillingPDF is not affiliated with, endorsed by, or connected to the General Services Administration (GSA). Get the official form from the General Services Administration (GSA) website.

Form GSA 184B, Construction Progress Report (Change Order Breakdown)

GSA 184B is the General Services Administration's Construction Progress Report (Modification/Change Order Breakdown) for construction contracts. Fill out the form online on FillingPDF and download or print the completed PDF.
2 pages
Page 1 of 2
Page 2 of 2
Click a highlighted field to fill it in. Your data is deleted after 7 days.

GSA 184B, the Construction Progress Report (Modification/Change Order Breakdown), is a General Services Administration (GSA) form that lists each contract modification or change order with its value and the work completed on it. The contracting officer or an authorized representative prepares it for construction contracts, and it is completed before payment requests. On this page you can fill out the form online on FillingPDF and download or print the completed PDF; the official PDF is published by GSA at gsa.gov.

Last updated

What is GSA 184B?

Form GSA 184B, Construction Progress Report (Change Order Breakdown), is the General Services Administration (GSA) form that breaks a construction contract's modifications and change orders down by number and value and records how much work and stored material on each is complete. The title printed on the form is Construction Progress Report (Modification/Change Order Breakdown).

According to the instructions printed on the back of the form, GSA Form 184B provides part of the necessary documentation on construction progress. It is not a stand-alone progress record: it covers the modification and change-order side of a contract.

The form opens with a header block: PAGE OF PAGES, REPORT NUMBER, DATE, CONTRACT NUMBER and TASK ORDER NUMBER. Below it is a table with one row per modification and five numbered columns:

  • Column 1, Modification Number.
  • Column 2, Total Value of Modification in the contract.
  • Column 3, Value of Work Completed, split into sub-column (a), Previous Value, and sub-column (b), Current Value.
  • Column 4, Value of Materials.
  • Column 5, Total Value of Completed Work.

All dollar columns are marked "Dollars Only". The form carries the revision date GSA 184B (REV 10/2016).

Who needs to file GSA 184B?

GSA 184B is prepared by the contracting officer or his or her authorized representative. It is not a form that a contractor or member of the public completes on their own initiative.

The instructions say the form is used on all construction contracts awarded under new construction, repair and alteration programs, regardless of Delivery Method. If a construction contract of that kind has modifications or change orders, they are reported on this form.

The form is also tied to the contract it reports on: the header asks for the contract number and, where one exists, the task order number, so a separate report is kept for each contract or task order. The instructions name no other category of users and set out no exclusions beyond that contract scope.

When to file GSA 184B

Complete GSA 184B promptly before payment requests. The instructions say a copy of the form shall be completed promptly prior to payment requests, so each payment request on a construction contract is preceded by a current report.

The instructions also require the information on the form to be kept current. Because column 3 separates the amount completed through the previous report, in sub-column (a), from the amount completed since that report, in sub-column (b), each new report builds on the one before it, and the REPORT NUMBER and DATE in the header identify where it falls in the sequence. The form prints no separate calendar deadline.

How to fill out GSA 184B

  1. Enter report number, date and page count

    In the top block, fill in REPORT NUMBER, DATE and PAGE OF PAGES so the report can be placed in the sequence of reports for the contract.

  2. Identify the contract and task order

    Enter the CONTRACT NUMBER and, where one applies, the TASK ORDER NUMBER in the header.

  3. List each modification in column 1

    In column 1, Modification Number, enter one modification or change order per row.

  4. Enter total modification value in column 2

    In column 2, enter the total value of that modification in the contract, in dollars only.

  5. Enter previous completed work in column 3(a)

    In sub-column (a), enter the cumulative amount completed through the previous report, in dollars only.

  6. Enter current completed work in column 3(b)

    In sub-column (b), enter the current amount completed since the previous report, in dollars only.

  7. Enter materials value in column 4

    In column 4, Value of Materials, enter the value of materials stored during the construction phase.

  8. Enter total completed work in column 5

    In column 5, enter the value of work in place and stored materials for the modification, as the instructions describe it.

  9. Review and download the completed PDF

    Check that the report is current and that every figure sits in its proper column, then download or print the completed PDF from FillingPDF for the contracting officer's use.

How to submit GSA 184B

The form names no mailing address, portal or appointment process of its own. What it states is the timing and the preparer: the contracting officer or an authorized representative completes a copy promptly prior to payment requests, and the form is part of the documentation on construction progress.

  • Before a payment request: complete the report so that it is current when the payment request is made.
  • Where it goes: follow the contract and the contracting officer's instructions for how the report accompanies payment documentation, since the form itself prints no channel.

FillingPDF lets you fill out and download the PDF; submission follows the channels the contracting officer and the contract set.

Common mistakes to avoid

  • Completing the report after a payment request instead of promptly before it, as the instructions require.
  • Letting the figures go out of date; the instructions say the information on the form must be kept current.
  • Entering cents in the dollar columns, which are marked "Dollars Only".
  • Putting the cumulative amount through the previous report in sub-column (b) of column 3 instead of sub-column (a), or the reverse.
  • Entering the value of stored materials in column 5 instead of column 4, which is for materials stored during the construction phase.
  • Leaving the contract number or the task order number blank in the header when the report relates to them.
  • Having someone other than the contracting officer or an authorized representative prepare the form.

Frequently asked questions

What is GSA Form 184B used for?

GSA 184B is the Construction Progress Report (Modification/Change Order Breakdown). It lists each contract modification or change order with its total value, the work completed and the materials stored, and provides part of the documentation on construction progress.

Who fills out GSA 184B?

The contracting officer or his or her authorized representative prepares the form, according to the instructions printed on it. It is a contract-administration document rather than an application made by a contractor or the public.

Which contracts need a GSA 184B construction progress report?

The instructions say the form is used on all construction contracts awarded under new construction, repair and alteration programs, regardless of Delivery Method.

When do I complete GSA 184B?

Promptly before payment requests. The instructions say a copy of the form is completed prior to payment requests, and that the information on it must be kept current. The form prints no fixed calendar date.

What goes in column 3 of GSA 184B?

Column 3 is the value of work completed. Sub-column (a) is the cumulative amount completed through the previous report; sub-column (b) is the current amount completed since the previous report. Both are in dollars only.

What is the difference between columns 4 and 5?

Column 4 is the value of materials stored during the construction phase. Column 5 is the value of work in place and stored materials, according to the instructions printed on the back of the form.

Can I fill out GSA 184B online?

Yes. You can fill out the PDF online on FillingPDF and download or print it. FillingPDF is an independent service and does not send the report to GSA; it follows the contracting officer's and the contract's channels.