How to Obtain a Certificate of Occupancy (C/O) is the Cobb County Community Development Agency's guide for commercial businesses that need a C/O for a new or existing space. It lays out five steps, from the Commercial Permit Application to the final inspections, and the Information Change Process for eligible tenants. Do not confuse it with a Cobb County business license: the guide states that an Occupation Tax Certificate (Business License) is NOT a Certificate of Occupancy. On this page you can fill out the form online on FillingPDF and download or print the completed PDF; the original guide is published by Cobb County at the official URL.

Last updated

What is How to Obtain a Certificate of Occupancy (C/O) – Cobb County, GA?

How to Obtain a Certificate of Occupancy (C/O) is the Cobb County Community Development Agency guide that walks commercial businesses through the steps required to obtain a Certificate of Occupancy for a new or existing commercial space in Cobb County, Georgia.

The guide says all commercial businesses require a valid C/O and cites Official Code of Cobb County, Chapter 18, Article VIII, Section 18-234. It offers two routes:

  • Option 1: New C/O. You obtain a new Certificate of Occupancy with a new business name, starting with step 1 of the guide.
  • Option 2: Information Change. If no changes are made to the interior or exterior of a tenant space (other than cosmetic), the occupant load, or the business type, you may be eligible to submit an Information Change Form (ICF) to the Fire Marshal's Office (FMO) instead.

The five steps are: complete a Commercial Permit Application (CPA); get Cobb County Water System (CCWS) approval; contact Cobb & Douglas Public Health, which is not required for all businesses; obtain Fire Marshal review and approval; and, once all applicable final inspections are passed, obtain the C/O from the Community Development Agency.

The guide is explicit that an Occupation Tax Certificate (Business License) is not a C/O. The two are separate documents, and the guide says to display or store your C/O and Business License in an easily accessible location. It also states that verifying compliance with the county and state departments it lists is the applicant's responsibility.

Who needs to file How to Obtain a Certificate of Occupancy (C/O) – Cobb County, GA?

Commercial businesses opening in a commercial building, new or existing, need a valid Certificate of Occupancy; the guide says all commercial businesses require one. A business moving into a space with a new business name follows Option 1 and begins with the Commercial Permit Application.

Tenants may instead qualify for the Information Change Process when all four criteria are met:

  • a valid C/O exists for the space being moved into;
  • the tenant space has the same occupant classification as the previous occupant;
  • no changes to the occupancy are proposed;
  • no work without a permit was performed.

Not all businesses are eligible. The guide lists common reasons for ineligibility: no previous C/O available; any construction, including mechanical, electrical or plumbing (cosmetic work such as painting is acceptable); drawings that do not match previous floor plans; a significant change in furniture layout, especially for restaurants; and a change of use that modifies the occupant load, such as an insurance business becoming a tutoring business.

Businesses serving food have an extra step with the CCWS. A general contractor hired for the project must also supply certain licenses, as described in the required documents. This guide does not replace a business license, which is a separate Occupation Tax Certificate.

When to file How to Obtain a Certificate of Occupancy (C/O) – Cobb County, GA

Start the process when you are opening a new business in an existing commercial building, or when a tenant space changes business name, because the guide says all commercial businesses require a valid C/O. The first step is the Commercial Permit Application.

The C/O itself is obtained only after all applicable final inspections, including building, FMO, arborist, CCWS and special inspections, have been completed and passed. The guide says Fire Marshal plan reviews are generally scheduled within 2 weeks of when all documents are received. All CCWS fees must be paid before a building permit is issued, and the C/O fee is included at the time of permit issuance.

If general contractor bids are still being collected, the Building Department will accept the application without the contractor's information and the Authorized Agent form, but the hired contractor must submit them before a permit is issued. The guide sets no other deadline for this process.

Documents you need

  • Commercial Application (Commercial Permit Application), completed entirely with applicable information; the guide says required documents may include but are not limited to those listed.
  • Scope of Work letter: a 1-page summary of proposed construction or non-construction activities.
  • Virtual set of plans; if larger than 20MB, request a "shared folder" in the application submittal.
  • Copy of the applicant's driver's license.
  • Copy of the General Contractor's Georgia state license and business license, if applicable; the hired contractor must submit it before a permit is issued.
  • Authorized agent form, which the hired general contractor must submit before a permit is issued.
  • Food service establishments (FSE) application, for any business serving food.
  • Commercial Permit Application and all drawings submitted to the Fire Marshal's Office, for Fire Marshal review.
  • For an Information Change Form: all required information the form asks for, including drawings and pictures the FMO may compare against previous floor plans.

How to fill out How to Obtain a Certificate of Occupancy (C/O) – Cobb County, GA

  1. Choose a new C/O or ICF

    Option 1 is a new C/O with a new business name; Option 2 is the Information Change Form for tenant spaces with no non-cosmetic interior or exterior changes, no occupant load change and no business type change.

  2. Complete the Commercial Permit Application

    Step 1: read all pages of the Commercial Permit Application at www.cobbcounty.org/comdev and complete it entirely with applicable information.

  3. Gather the supporting documents

    Prepare the Scope of Work letter (1 page), the virtual set of plans, a copy of your driver's license and, if applicable, the general contractor's Georgia licenses and the Authorized agent form.

  4. Get Cobb County Water System approval

    Step 2: CCWS plan review contacts you if more information is needed. Plan for a testable backflow assembly after the water meter, and pay all CCWS fees before the building permit is issued.

  5. Add the food service application

    If your business serves food, also submit the FSE application and schedule a new trap inspection with the Grease Management Office before installation.

  6. Contact Cobb & Douglas Public Health

    Step 3: contact the office at (770) 435-7815 for approval. This is not required for all businesses, and fees may apply.

  7. Submit to the Fire Marshal's Office

    Step 4: send the Commercial Permit Application and all drawings online at www.cobbfmo.org, and schedule inspections through the 'Mobile Eyes Contractor Portal'.

  8. Prepare for the fire inspection

    Check the guide's Top 10 Fire Code Violations list, including posted address, extinguisher, sprinkler and fire alarm inspections, egress door locks, exit signage and fire lane markings.

  9. Obtain the Certificate of Occupancy

    Step 5: once all applicable final inspections have passed, request the C/O from the Community Development Agency at [email protected].

  10. Use the Information Change Process if eligible

    If all four ICF criteria are met, go to www.cobbfmo.org, select 'Certificates of Occupancy/Plan Review' and then 'Information Change Form', and submit all required information.

  11. Review and download the completed PDF

    Check every entry against the guide, then download or print the completed PDF from FillingPDF and submit through the channels described under How to submit.

How to submit How to Obtain a Certificate of Occupancy (C/O) – Cobb County, GA

The process runs through several Cobb County offices, mostly online, by email and by phone. The guide gives these channels:

  • Commercial Permit Application: located at www.cobbcounty.org/comdev. Questions: (770) 528-2071 | [email protected]. If your plans are larger than 20MB, request a "shared folder" in the application submittal.
  • Cobb County Water System: plan review may contact you during permitting. (770) 419-6324 | [email protected]. Food service businesses also submit a food service establishments (FSE) application, found at https://www.cobbcounty.org/water/compliance/grease-management/fse.
  • Cobb & Douglas Public Health: (770) 435-7815 | https://cobbanddouglaspublichealth.com/environmental-health/. Not required for all businesses.
  • Fire Marshal's Office (FMO): submit the Commercial Permit Application and all drawings online at www.cobbfmo.org; inspections are scheduled through the 'Mobile Eyes Contractor Portal'. (770) 528-8310.
  • Certificate of Occupancy: after all final inspections pass, obtain it by email from the Community Development Agency at [email protected].
  • Information Change Form: at www.cobbfmo.org, select 'Certificates of Occupancy/Plan Review', scroll to Plan Review Resources and select 'Information Change Form'. The FMO contacts you by email after submission.

Fees apply at several stages (permitting, CCWS, FMO, possibly Public Health, and the ICF). The guide gives no amounts, so ask each office. FillingPDF lets you fill out and download the PDF; submission follows the channels above.

Common mistakes to avoid

  • Treating an Occupation Tax Certificate (Business License) as a Certificate of Occupancy; the guide says a business license is not a C/O.
  • Submitting an Information Change Form after construction of any kind, including mechanical, electrical or plumbing work; only cosmetic work such as painting is acceptable.
  • Expecting an Information Change Form to change the registered business name on the C/O; it changes contact information only.
  • Hiring a general contractor but not supplying their Georgia business license, state license and Authorized agent form before the permit is issued.
  • Not paying all CCWS fees before the building permit is issued.
  • Opening a food service business without submitting the FSE application or scheduling the new trap inspection before installation.
  • Leaving out the testable backflow assembly after the water meter on a commercial water service (domestic, irrigation or fire).
  • Asking for the C/O before all applicable final inspections have been completed and passed.
  • Uploading plans larger than 20MB without requesting a "shared folder" in the application submittal.

Frequently asked questions

What is a Certificate of Occupancy (C/O) in Cobb County?

It is the certificate all commercial businesses in Cobb County require. The Community Development Agency's guide explains how to obtain one for a new or existing commercial space, after permitting, water, fire marshal and final inspections are completed and passed.

Is a Cobb County business license the same as a Certificate of Occupancy?

No. The guide states that an Occupation Tax Certificate (Business License) is not a Certificate of Occupancy. A new business in an existing commercial building needs the C/O process described here, and you should display or store both documents where they are easy to reach.

How do I get a Cobb County business license?

The county's business license page says to determine whether your business is in unincorporated Cobb County, complete the application packet for your business type (all documents signed by the same person), and email it to [email protected] to get the fee amount for a new business establishment.

Can I skip a new C/O if I'm moving into a space that already has one?

Possibly. If a valid C/O exists, the occupant classification is the same, no occupancy changes are proposed and no work without a permit was done, you may be eligible to submit an Information Change Form to the Fire Marshal's Office. Not all businesses qualify.

Does the Information Change Form change my business name on the C/O?

No. The guide says the ICF process changes contact information only and does not change the registered business name listed on the C/O. A new business name requires Option 1, a new Certificate of Occupancy.

How long does Fire Marshal plan review take?

The guide says plan reviews are generally scheduled within 2 weeks of when all documents are received. It gives no overall processing time for the C/O, which is issued only after all applicable final inspections have been completed and passed.

Are there fees to get a Certificate of Occupancy in Cobb County?

Yes, fees apply at several stages: permitting, CCWS, Fire Marshal plan review and inspections, possibly Public Health, and the ICF. The C/O fee is included when the permit is issued. The guide gives no amounts, so contact each office.

Where do I ask for my C/O once inspections are done?

Email the Community Development Agency at [email protected] after all applicable final inspections, including building, FMO, arborist, CCWS and special inspections, have been completed and passed.

Can I fill out this Cobb County C/O guide online on FillingPDF?

You can fill out the PDF online on FillingPDF and download or print it. FillingPDF is an independent service, not connected to Cobb County, and does not file anything; you use the county's channels to apply.

Ready to fill out How to Obtain a Certificate of Occupancy (C/O) – Cobb County, GA?

Fill out How to Obtain a Certificate of Occupancy (C/O) – Cobb County, GA now